Dinas Pekerjaan Umum Provinsi Papua
REKAPITULASI KEGIATAN
Tahun :     Sumber Dana :        

SUMBER DANA : PAD
NO. NAMA UNIT KERJA NILAI KONTRAK
(Rp.)
BOBOT (%) KEMAJUAN PROYEK
FISIK KEUANGAN
REAL (%) REAL TTB(%) KEUANGAN (Rp.) %
1. BIDANG CIPTA KARYA DAN AIR BESIH 34.950.000 15.26 100.00 15.26 34.950.000 100.00
2. BIDANG JALAN DAN JEMBATAN 0 0.00 100.00 15.26 0 100.00
3. BIDANG PROGRAM DAN PERENCANAAN 0 0.00 100.00 15.26 0 100.00
4. BIDANG SUMBER DAYA AIR 0 0.00 100.00 15.26 0 100.00
5. PENG. TEKNIS & PENGEMB. KONSTRUKSI 0 0.00 100.00 15.26 0 100.00
6. SEKRETARIS DINAS 194.011.000 84.74 50.00 42.37 194.011.000 100.00
7. UPTD LABORATORIUM 0 0.00 50.00 42.37 0 100.00
BELANJA LANGSUNG 228.961.000 100.00 21.43 21.43 228.961.000 100.00
BELANJA TIDAK LANGSUNG 0 0.00     0 0.00
TOTAL KESELURUHAN 228.961.000 100.00     228.961.000 100.00